November ’22 Construction Update

November '22 Construction Update

 


 
Works on site continue to progress well, with the significant milestone of the installation of the lifts being achieved. 

We’ve also made headway on:

• Lower ground and ground floor amenities being fitted out
• Glazing of the ground floor level
• Level 1 stone installation commencing
• Level 1 timber flooring continuing to be installed
• Level 2 service fit-off
• Level 4 tiling being completed
• Level 5 joinery install commencing
• Level 7 first coat of paint being completed; and
• The northern river embankment external works commencing