July ’22 Construction Update
With the milestone of ‘topping out’ behind us, we are now focusing on the following:.
Current Status
• Level 7 glass installation
• Level 6 high-level service rough-in
• Level 4 framing of walls
• Level 3 balustrade glass
• Level 3 plastering; and
• Level 1 external waterproofing to start this week
You can continue to view the site via our timelapse camera through the Walmer Purchaser Portal to see first-hand the works being completed.
To log into the portal please click here or on any of the images above and enter your apartment number, with your password being your email address.