September ’22 Construction Update
September has seen momentum increase immensely with framing and plastering bringing shape to the internal structure.
• Level 1 works have included
– Corridor ceiling grid being hung
– Paving and tanking started on terraces; and
– Joinery installation has begun
We also have underway:
• Level 2 sealer coat for walls and ceilings
• Level 3 second coat of plaster stopping
• Level 4 base coat plastering
• Level 5 sheeting walls and ceilings
• Level 6 roughing in services being completed with carpentry fix also commenced
And completed:
• Level 7 rough in services; and
• Level 8 wall framing with noggins
You can continue to view the site via our timelapse camera through the Walmer Purchaser Portal to see first-hand the works being completed.